Problem: A facilities manager with a national maintenance company called looking for a corporate solution for their wash pads. They were expanding into several new markets and wanted to standardize their washing and water treatment systems.

Complications included the fact that most of their vehicles are sweeper trucks which generate a lot of solids. A typical wash yields 1/3 yard of solids. With each facility washing 10+ units per day, the amount of solids generated per month was substantial. Also, each facility has a slightly different layout. The good news was that most of them were connected to the municipal sewer.

Solution:  Since their solids handling issues needed to be addressed in addition to their washing and water treatment issues, we offered our engineering services to help them design a custom solution that they could standardize as much as possible for their wash bays and solids settling basins.

Once we completed the design, we recommended a number of washing and treatment options based on their desired washing processes.  Due to the fact that they had a variety of vehicles and equipment, they decided on both a demucking system and pressure washing system for washing. The demucking system was paired with a partial water reclaim system to recycle the water multiple times before the water was sent through our SPT-20 Clarifier Oil Water Separator System to process it for acceptable discharge to the sewer.

Finally, all of the equipment was installed in a TER-20 Transportable Equipment Room. This will save installation costs as well as allow the customer to move the equipment to a different location in the future. It also saves space inside of the customer’s building for other critical activities.

 


June 9, 2017

Case Study – Rental Equipment
portable equipment room

Problem: An equipment rental company specializing in heavy-duty construction equipment needed to build a wash bay for their haul trucks, dozers and construction vehicles. They had limited inside space in a leased building so they needed a to put all of the equipment inside a portable equipment room that they could pick up and move if needed. Due to their location in a remote area with no sewer connection, they needed a closed loop wash water treatment system.

The company called and asked us to build a heavy-duty, self-contained washing system and help them design the wash pad and solids settling area.

Solution: We had worked with this client for years so we were well aware of the washing and solids handling complications associated with heavy construction equipment. With input from the client, our engineers designed a wash pad design and solids settling system that fit into a rather tight footprint.

All of the wash equipment including a closed loop wash water reclaim system, an electric pressure washing system, and a demucking system was installed in a 40’ Transportable Equipment Room (TER-40) and located adjacent to the wash pad. This saved building costs, preserved valuable warehouse space and will allow them to move the entire system to a different facility if needed.

wash pad design

transportable equipment room


North Carolina

Headquarters

At WashBaySolutions.com, we have been specializing in high tech, custom-engineered solutions to complex washing and wastewater issues since 1991.
+ 1 800-453-8639

WashbaySolutions.com

sales@washbaysolutions.com

GET IN TOUCH

Follow Our Activity

Get the latest news, product updates and case studies all happening here: